How Much Deposit Can a Builder Ask For? The Limit in Each State

The most a builder can ask you to pay before work starts in New South Wales, Queensland, Victoria, Western Australia, South Australia and Tasmania, with a calculator for your contract price, Victoria's stage payments and the cooling-off periods we could read.

Updated

A homeowner and a site foreman stand beside the formwork and steel mesh of a house slab

Before any money leaves your account

  • The deposit is capped by state law, and the cap shrinks as the job gets bigger.
  • The cap is a percentage of the contract price. It is not a number the builder gets to name.
  • Later payments have to follow the work done. A date on a calendar is not a reason to pay.

What is the most you can be asked to pay up front?

$

The figures were taken from official pages opened on 14 November 2026. What you see is the legal ceiling, not the usual deposit, and asking for less is always allowed.

Ceilings, cooling-off and the page each comes from

StateDeposit ceilingCooling-offWhere we read it

The ACT and the Northern Territory carry no figure because we could not read an official page for them.

Victoria spells out the later payments too

For a full build the Victorian page lists the most a builder may ask at each stage, as a share of the total price. Each share is paid when that stage is complete.

Contract coversBaseFrameLock-upFixing
Build to lock-up20%25%n/an/a
Build to fixing12%18%40%n/a
Build all stages10%15%35%25%

Consumer Affairs Victoria, deposits and payments page, updated 9 July 2025. The abbreviation n/a means that stage is not part of that kind of contract.

Paying as the work goes

  1. Tie each payment to something you can see. Queensland says all progress payments must relate to the amount of work completed, and Western Australia says they should cover only work done or materials supplied.
  2. Hold the half-way line in Queensland. The contractor cannot claim more than 50 percent of the price, deposit included, until at least half the onsite work is complete.
  3. Do not pay ahead of the contract date or above the contract amount. The QBCC page says so in as many words.
  4. Get the insurance first where it applies. In New South Wales a builder may not take a deposit on work over $20,000 until the cover exists, and the home warranty insurance guide shows where each state draws that line.

Limits of this deposit guide

It is not legal advice, and it does not cover owner-builders or commercial work. Several of these rules were changed in 2025. A Victorian amending law passed on 11 September 2025 had no start date on the page we opened, so the Victorian row is the one to confirm first. Tasmania was read from the text of the Act through a summary, and the ACT and the Northern Territory were not opened. See how BuildTradie chooses for how we handle official pages.